From 2018 to 2025 Morocco went through seven consecutive years of drought. Dams fell to historic lows, some towns faced water cuts, and farmers in several regions lost harvests. Heavy rain in late 2025 and early 2026 changed the picture, and in January 2026 the water minister declared the drought over. The long-term response, however, goes beyond waiting for rain. It rests on two big ideas: moving water from wetter basins to drier ones, and producing drinking water from the sea.
The "water highway"
The first inter-basin transfer, often called the water highway, links the Sebou basin in the north with the Bouregreg basin that supplies Rabat and Casablanca.
- Length: about 67 km of pipes and pumping stations.
- Cost: about MAD 6 billion.
- In service: since the end of August 2023, built in under a year.
- Volume moved: about 954 million cubic metres by December 2025, according to MENA Water Review.
The water it carries would otherwise have flowed to the sea during wet periods. In dry years it helped keep taps running in the Rabat–Casablanca corridor.
The next stage
In November 2026, Equipment and Water Minister Nizar Baraka said a second link, from the Bouregreg to the Oum Er-Rbia basin, would start early in 2027 with an initial capacity of 400 million m³ a year, to be doubled later. That would carry northern water further south, towards the Marrakech-Safi and Casablanca-Settat regions. At the same time he put national dam reserves at about 11.2 billion m³, much higher than during the drought years.
Desalination: water from the Atlantic and the Mediterranean
Morocco has about 17 desalination plants producing roughly 350 million m³ a year, and the government aims to reach about 1.8 billion m³ a year by 2031.
Chtouka (Agadir)
In service since 2022, the Chtouka plant produces about 275,000 m³ a day, of which 125,000 m³ goes to farm irrigation in the Chtouka plain. It is designed to expand to 400,000 m³ a day. It was one of the first plants in the world to share output between drinking water and agriculture on this scale.
Casablanca
The largest project is the Casablanca plant, under construction since June 2024 at a cost of about $650 million. Its first phase, at 200 million m³ a year, is planned for February 2027, and a second phase would bring it to 300 million m³ in 2028. It is to run on renewable electricity and serve about 7.5 million people.
Other planned plants
- Nador: about 300 million m³ a year
- Tangier: about 150 million m³, as a public-private partnership
- Tiznit: about 350 million m³, planned for 2027
- Tan-Tan and Guelmim: about 100 million m³, planned for 2027
Why it matters even after the rain
A wet year refills dams, but the long-term trend is less rainfall and higher temperatures. The new infrastructure is meant to make cities less dependent on any single rainy season, and to free dam water for agriculture.
There are trade-offs. Desalination uses a lot of energy, which is why the new plants are being linked to wind and solar power. It also produces brine that has to be discharged carefully, and it makes water more expensive to produce than dam water.
What you can do locally
Even with recovering reserves, municipalities still apply restrictions in some areas, such as limits on washing cars or filling pools. Check announcements from your local water distributor or regional multiservice company, and report leaks on public networks.